Service Panel Preparation
  1. Power off the Service Panel, and ensure power is completely off with multi-voltage meter.
  2. Disconnect Breaker's wire(s)
    3-Phase 3-Poles breaker:
    1. Test the unit for power.
    2. Disconnect one of the wire from the 3-Poles breaker.
    3. Label the wire such as "L1-TnkLess Heater".

    1-Phase 2-Poles breaker:
    1. Test the unit for power.
    2. Disconnect one of the wire from the 2-Poles breaker.
    3. Label the wire such as "L1-Stove".

    1-Phase 1-Pole break:
    1. Test the unit for power.
    2. Disconnect the wire from the breaker.
    3. Label the wire such as "L1-PorchLight".
  3. Align the NiteWatt panel and knock out 2 holes.
    Connection
  1. Connect the income wires consecutively to the relay-switches.
  2. Run new wires from the relay-switches back to the breakers.
    Recap: starting from the top where label 1, 2 and 3 from the Main Service Panel. All disconnected wires tunnel through the NiteWatt Service Panel and connect to the relay-switches. Then from there back to the breaker to complete the circuit.
    Main Logic Controller
  1. Verify connection of red (positive) wires between relay-switches and the Main Logic Controller.
  2. Verify connection of black wires from Main Logic Controller to all relay-switches.
  3. Verify wires connection to the battery and the Main Logic Controller.
    Notes: NiteWatt will come pre-wired. Base version is easier.
    Solar Power
  1. Mount the provided solar panel South facing, then connect the power cord.
  2. Verify firm connection and light status of the battery.
  3. Verify firm connection to the Main Logic Controller. A Beep should given to confirm connection. Green light confirms operational status.
    Notes: NiteWatt will come pre-programmed or custom configuration base on the service agreement.